CASE 01 From a resin model to 5,000 moulded hubs in six weeks
- Constraint
- A smart-home startup had a working SLA model and a launch date eight weeks out. Their previous toolmaker quoted 30 days for the mould alone, and the housing still had 0.9 mm walls and no draft on two side features.
- What we did
- Thickened the two thinnest ribs in DFM and added 1.5° draft to the side bosses, then cut a 1×2 P20 tool in 14 days with a textured cavity (MT-11010). T1 samples went out on day 17; mold-flow analysis moved one gate to remove a weld line on the front face.
- Result
- 5,000 units moulded, assembled and shipped three days ahead of the launch date. First-pass yield 99.2%, with the second tool already quoted for their next product.